Gedung B25 dan B27 di pusat data China Mobile, Hohhot, dilaporkan rampung pada Oktober 2026; tanggal commissioning belum diumumkan. Kapasitas total 20.100P, termasuk 16.700P untuk komputasi cerdas, merupakan angka yang diproyeksikan setelah fasilitas beroperasi.
Diterbitkan olehDiedit dengan GPT-6 LunaGambar dibuat dengan GPT Image 2
Jawaban penelitian

Create a landscape editorial hero image for this Studio Global article: What are the full details of China Mobile’s Hohhot intelligent computing center expansion reported on October 12, 2026, including its comple. Article summary: The October 12, 2026 report established that China Mobile’s Hohhot B25/B27 expansion had completed construction—not that the expanded capacity was already operational; the stated 20,100P capacity was explicitly condition. Topic tags: general, general web. Style: premium digital editorial illustration, source-backed research mood, clean composition, high detail, modern web publication hero. Use reference image context only for broad subject, composition, and topical grounding; do not copy the exact image. Avoid: logos, brand marks, copyrighted characters, real person likenesses, fake screenshots, UI text, readable text, watermarks, charts with fake numbers, clic
Ekspansi pusat data China Mobile di Hohhot, Mongolia Dalam, dilaporkan telah selesai dibangun. Namun, rampungnya konstruksi tidak otomatis berarti kapasitas tambahan sudah beroperasi. Laporan 12 Oktober 2026 menyebut kapasitas pusat tersebut akan mencapai 20.100P setelah mulai beroperasi, tanpa mencantumkan tanggal commissioning. 17
Proyek ini mencakup gedung B25 dan B27 di pusat data China Mobile, kawasan baru Horinger, Mongolia Dalam. Konstruksinya dikerjakan China Construction Third Engineering Bureau. Nilai kontraknya dilaporkan sebesar 2,7 miliar yuan, dengan luas bangunan sekitar 44.500 meter persegi dan daya IT 120 MW. 17
Angka 120 MW merujuk pada daya IT proyek, bukan total konsumsi listrik seluruh kompleks. Laporan menyebut pembangunan baru-baru ini selesai, tetapi tidak memastikan tanggal persis penyelesaian maupun kapan fasilitas mulai beroperasi. 17
Setelah ekspansi mulai beroperasi, kapasitas totalnya diproyeksikan mencapai 20.100P, termasuk 16.700P untuk komputasi cerdas. Laporan juga menyebut 90% kapasitas komputasi akan melayani kawasan Beijing–Tianjin–Hebei dan porsi listrik hijau mencapai 88%. Angka-angka tersebut merupakan klaim proyek, bukan bukti bahwa gedung baru sudah beroperasi penuh. 17
Sejumlah laporan berbahasa Inggris menuliskan kapasitas total itu sebagai 20.100 petaflops. 2
13 Namun, sumber yang tersedia tidak merinci presisi numerik, format perhitungan, atau kondisi tolok ukur. Karena itu, angka tersebut belum cukup untuk membandingkan kinerja secara langsung dengan sistem lain.
17
Ekspansi Hohhot disebut sebagai bagian dari program nasional “Eastern Data, Western Computing”—yang mengarahkan pemrosesan data ke wilayah barat—serta simpul inti dalam jaringan komputasi China Mobile “4+N+31+X”. Proyek ini juga digambarkan sebagai proyek penting dalam jaringan komputasi nasional terpadu. 17
9
Laporan menyebut koneksi melalui tulang punggung jaringan 400G OTN, dengan latensi transmisi satu arah dari Hohhot ke Beijing sebesar 3,5 milidetik. 17
9 Angka tersebut saja belum memastikan kecocokan untuk semua aplikasi yang sensitif terhadap latensi. Kinerja ujung ke ujung juga dipengaruhi waktu pemrosesan, latensi pulang-pergi, dan kebutuhan layanan tertentu.
Proyek ini turut disebut sebagai pusat komputasi cerdas satu lokasi terbesar di dunia yang dioperasikan oleh perusahaan telekomunikasi. Klaim itu merujuk pada skala pusat milik operator—bukan pernyataan terverifikasi bahwa fasilitas tersebut adalah pusat AI terbesar dalam kategori apa pun. 17
Angka 88% untuk porsi listrik hijau tercantum dalam laporan ekspansi, tetapi sumber tidak menjelaskan periode penghitungannya atau memastikan bahwa angka itu mencerminkan konsumsi aktual gedung B25 dan B27. 17 Secara terpisah, laporan pemerintah Hohhot menyebut pusat yang sudah ada membeli 750 juta kWh listrik hijau pada 2025 melalui pasokan langsung dan perjanjian pasar listrik jangka menengah maupun panjang. Angka historis itu bukan pengukuran konsumsi listrik B25 dan B27.
22
Xinhua juga melaporkan adanya stasiun tenaga angin, surya, dan penyimpanan energi milik Huadian yang memasok perusahaan komputasi. Kawasan komputasi Horinger disebut berjarak sekitar 41 kilometer dari stasiun tersebut. Informasi ini memberi konteks regional, tetapi bukan jarak pasti dari gedung B25 atau B27 ke instalasi pemasok tertentu. 24
Laporan yang tersedia berbeda mengenai kapan pusat data Hohhot yang sudah ada mulai beroperasi: IT Home menyebut Desember 2025, sementara profil fasilitas lain mencantumkan 28 April 2024. Sumber-sumber tersebut tidak menjelaskan perbedaan tanggal itu ataupun mengaitkannya dengan commissioning B25 dan B27. 17
36
Untuk fasilitas yang sudah ada, laporan sebelumnya menyebut sekitar 20.000 kartu akselerator AI. Angka porsi chip AI domestik juga berbeda: lebih dari 85% menurut IT Home dan lebih dari 89% dalam laporan Xinhua pada Juni 2026. Kedua keterangan itu tidak dinyatakan sebagai spesifikasi gedung baru. 17
39
Pendinginan cair cold-plate dan PUE serendah 1,15 juga dilaporkan untuk fasilitas Hohhot yang sudah ada, bukan secara jelas sebagai hasil pengukuran kinerja ekspansi B25 dan B27. Sumber yang tersedia tidak memverifikasi penggunaan GPU pooling maupun memberikan angka PUE rata-rata untuk gedung baru tersebut. Klaim terpisah mengenai peringkat klaster tunggal pusat di Harbin juga tidak didukung oleh informasi yang tersedia di sini, sehingga kedua klaim skala itu tidak dapat dibandingkan secara meyakinkan. 17
Inti kabarnya adalah perbedaan antara konstruksi dan operasi: B25 dan B27 dilaporkan telah rampung, sedangkan kapasitas 20.100P masih bergantung pada dimulainya operasi. 17
Studio Global AI
Halaman ini berisi jawaban yang didukung sumber yang dapat Anda lanjutkan di dalam Studio Global.
Gedung B25 dan B27 di pusat data China Mobile, Hohhot, dilaporkan rampung pada Oktober 2026; tanggal commissioning belum diumumkan.
Gedung B25 dan B27 di pusat data China Mobile, Hohhot, dilaporkan rampung pada Oktober 2026; tanggal commissioning belum diumumkan. Kapasitas total 20.100P, termasuk 16.700P untuk komputasi cerdas, merupakan angka yang diproyeksikan setelah fasilitas beroperasi.
Proyek ini memiliki daya IT 120 MW dan disebut akan melayani kawasan Beijing–Tianjin–Hebei serta menggunakan listrik hijau sebesar 88%.
Gedung B25 dan B27 di pusat data China Mobile, Hohhot, dilaporkan rampung pada Oktober 2026; tanggal commissioning belum diumumkan. Kapasitas total 20.100P, termasuk 16.700P untuk komputasi cerdas, merupakan angka yang diproyeksikan setelah fasilitas beroperasi.
Diterbitkan olehDiedit dengan GPT-6 LunaGambar dibuat dengan GPT Image 2
Jawaban penelitian

Create a landscape editorial hero image for this Studio Global article: What are the full details of China Mobile’s Hohhot intelligent computing center expansion reported on October 12, 2026, including its comple. Article summary: The October 12, 2026 report established that China Mobile’s Hohhot B25/B27 expansion had completed construction—not that the expanded capacity was already operational; the stated 20,100P capacity was explicitly condition. Topic tags: general, general web. Style: premium digital editorial illustration, source-backed research mood, clean composition, high detail, modern web publication hero. Use reference image context only for broad subject, composition, and topical grounding; do not copy the exact image. Avoid: logos, brand marks, copyrighted characters, real person likenesses, fake screenshots, UI text, readable text, watermarks, charts with fake numbers, clic
Ekspansi pusat data China Mobile di Hohhot, Mongolia Dalam, dilaporkan telah selesai dibangun. Namun, rampungnya konstruksi tidak otomatis berarti kapasitas tambahan sudah beroperasi. Laporan 12 Oktober 2026 menyebut kapasitas pusat tersebut akan mencapai 20.100P setelah mulai beroperasi, tanpa mencantumkan tanggal commissioning. 17
Proyek ini mencakup gedung B25 dan B27 di pusat data China Mobile, kawasan baru Horinger, Mongolia Dalam. Konstruksinya dikerjakan China Construction Third Engineering Bureau. Nilai kontraknya dilaporkan sebesar 2,7 miliar yuan, dengan luas bangunan sekitar 44.500 meter persegi dan daya IT 120 MW. 17
Angka 120 MW merujuk pada daya IT proyek, bukan total konsumsi listrik seluruh kompleks. Laporan menyebut pembangunan baru-baru ini selesai, tetapi tidak memastikan tanggal persis penyelesaian maupun kapan fasilitas mulai beroperasi. 17
Setelah ekspansi mulai beroperasi, kapasitas totalnya diproyeksikan mencapai 20.100P, termasuk 16.700P untuk komputasi cerdas. Laporan juga menyebut 90% kapasitas komputasi akan melayani kawasan Beijing–Tianjin–Hebei dan porsi listrik hijau mencapai 88%. Angka-angka tersebut merupakan klaim proyek, bukan bukti bahwa gedung baru sudah beroperasi penuh. 17
Sejumlah laporan berbahasa Inggris menuliskan kapasitas total itu sebagai 20.100 petaflops. 2
13 Namun, sumber yang tersedia tidak merinci presisi numerik, format perhitungan, atau kondisi tolok ukur. Karena itu, angka tersebut belum cukup untuk membandingkan kinerja secara langsung dengan sistem lain.
17
Ekspansi Hohhot disebut sebagai bagian dari program nasional “Eastern Data, Western Computing”—yang mengarahkan pemrosesan data ke wilayah barat—serta simpul inti dalam jaringan komputasi China Mobile “4+N+31+X”. Proyek ini juga digambarkan sebagai proyek penting dalam jaringan komputasi nasional terpadu. 17
9
Laporan menyebut koneksi melalui tulang punggung jaringan 400G OTN, dengan latensi transmisi satu arah dari Hohhot ke Beijing sebesar 3,5 milidetik. 17
9 Angka tersebut saja belum memastikan kecocokan untuk semua aplikasi yang sensitif terhadap latensi. Kinerja ujung ke ujung juga dipengaruhi waktu pemrosesan, latensi pulang-pergi, dan kebutuhan layanan tertentu.
Proyek ini turut disebut sebagai pusat komputasi cerdas satu lokasi terbesar di dunia yang dioperasikan oleh perusahaan telekomunikasi. Klaim itu merujuk pada skala pusat milik operator—bukan pernyataan terverifikasi bahwa fasilitas tersebut adalah pusat AI terbesar dalam kategori apa pun. 17
Angka 88% untuk porsi listrik hijau tercantum dalam laporan ekspansi, tetapi sumber tidak menjelaskan periode penghitungannya atau memastikan bahwa angka itu mencerminkan konsumsi aktual gedung B25 dan B27. 17 Secara terpisah, laporan pemerintah Hohhot menyebut pusat yang sudah ada membeli 750 juta kWh listrik hijau pada 2025 melalui pasokan langsung dan perjanjian pasar listrik jangka menengah maupun panjang. Angka historis itu bukan pengukuran konsumsi listrik B25 dan B27.
22
Xinhua juga melaporkan adanya stasiun tenaga angin, surya, dan penyimpanan energi milik Huadian yang memasok perusahaan komputasi. Kawasan komputasi Horinger disebut berjarak sekitar 41 kilometer dari stasiun tersebut. Informasi ini memberi konteks regional, tetapi bukan jarak pasti dari gedung B25 atau B27 ke instalasi pemasok tertentu. 24
Laporan yang tersedia berbeda mengenai kapan pusat data Hohhot yang sudah ada mulai beroperasi: IT Home menyebut Desember 2025, sementara profil fasilitas lain mencantumkan 28 April 2024. Sumber-sumber tersebut tidak menjelaskan perbedaan tanggal itu ataupun mengaitkannya dengan commissioning B25 dan B27. 17
36
Untuk fasilitas yang sudah ada, laporan sebelumnya menyebut sekitar 20.000 kartu akselerator AI. Angka porsi chip AI domestik juga berbeda: lebih dari 85% menurut IT Home dan lebih dari 89% dalam laporan Xinhua pada Juni 2026. Kedua keterangan itu tidak dinyatakan sebagai spesifikasi gedung baru. 17
39
Pendinginan cair cold-plate dan PUE serendah 1,15 juga dilaporkan untuk fasilitas Hohhot yang sudah ada, bukan secara jelas sebagai hasil pengukuran kinerja ekspansi B25 dan B27. Sumber yang tersedia tidak memverifikasi penggunaan GPU pooling maupun memberikan angka PUE rata-rata untuk gedung baru tersebut. Klaim terpisah mengenai peringkat klaster tunggal pusat di Harbin juga tidak didukung oleh informasi yang tersedia di sini, sehingga kedua klaim skala itu tidak dapat dibandingkan secara meyakinkan. 17
Inti kabarnya adalah perbedaan antara konstruksi dan operasi: B25 dan B27 dilaporkan telah rampung, sedangkan kapasitas 20.100P masih bergantung pada dimulainya operasi. 17
Studio Global AI
Halaman ini berisi jawaban yang didukung sumber yang dapat Anda lanjutkan di dalam Studio Global.
Gedung B25 dan B27 di pusat data China Mobile, Hohhot, dilaporkan rampung pada Oktober 2026; tanggal commissioning belum diumumkan.
Gedung B25 dan B27 di pusat data China Mobile, Hohhot, dilaporkan rampung pada Oktober 2026; tanggal commissioning belum diumumkan. Kapasitas total 20.100P, termasuk 16.700P untuk komputasi cerdas, merupakan angka yang diproyeksikan setelah fasilitas beroperasi.
Proyek ini memiliki daya IT 120 MW dan disebut akan melayani kawasan Beijing–Tianjin–Hebei serta menggunakan listrik hijau sebesar 88%.