The A14 hub — designated Fab 25 — will eventually include four separate 1.4nm fabs on the Taichung site . Construction has already accelerated.
| Milestone | Date |
|---|---|
| Land lease application submitted | October 17, 2025 |
| Three construction permits secured | October 30, 2025 |
| Foundation pile construction began | November 5, 2025 |
| First fab building expected to complete | Before April 2027 (ahead of schedule) |
| Risk / trial production expected | Late 2027 |
| Volume mass production expected | Second half of 2028 |
The CTSP Administration Director confirmed on July 29, 2026, that construction is running ahead of its original schedule .
These figures were confirmed at TSMC's 2025 North American Technology Symposium and reiterated in mid-2026 earnings updates :
The A14 node uses second-generation gate-all-around (GAA) nanosheet transistors, a full-node evolution from N2. A version with backside power delivery (A14P) is expected later in the node's lifecycle .
TSMC has not published an official, confirmed customer list for A14. Supply-chain and media reports consistently name the following as likely early adopters :
TSMC's management stated in July 2026 that there is "strong interest from AI/HPC and smartphone customers" and that A14's development is "well ahead of N2 at the same stage" .
Caveat: The named customers come from supply-chain and media reports, not from TSMC's own disclosures. Apple, NVIDIA, AMD, and Qualcomm should be treated as reported but unconfirmed.